Special Projects Coordinator: Jeff Ferguson
Overview
Minor repairs were completed this winter. Most large projects need to be done during the summer months.
Routine Maintenance
Brew
- Replaced broken window latch
- New hole for outhouse needed in near future?
Phelix
- A group made repairs to the roof in October.
- Assessed mildew. Took measurements for exposed wood surface area in order to calculate how much paint is needed. Interior painting to be done in summer 2009.
- Measurements taken and details recorded on the solar panel. Roland plans to do something with this. Batteries are dead beyond repair.
Harrison
- discussion about replacing/renovating the outhouse. Nothing confirmed.
- Trail design and location in progress. Pete Hudson in charge.